STAGE |
DESCRIPTION |
PERCENTAGE |
1 |
After signing the contract |
10 |
2 |
After finishing the design, get permission to build and complete the foundation |
20 |
3 |
After finishing 1st floor beam structure |
10 |
4 |
After finishing 2nd floor beam structure |
10 |
5 |
After finishing the structure of the tum, terrace and roof |
15 |
6 |
After finishing build brick wall |
10 |
7 |
After finishing install M&E equipment |
12 |
8 |
After installing electrical equipment, sanitary equipment, furniture, finishing cleaning works and finish project |
10 |
9 |
After 12 month of hanging over the project |
3 |